Energy References
COMBINED CYCLE POWER PLANT 252 MW
CUSTOMER: GLOBAL 3
YEAR: 2005 – 2007
LOCATION: Escatrón (Zaragoza), Spain
PROJECT: Combined Cycle power Plant “Peaker Power Plant” based on four gas turbines (4 GT), heat recovery boilers (4 HRSG) with auxiliary burners and condensation steam turbine. Water-cooled condenser with forced-throw wet cooling tower.
SERVICES: Property engineering, pre-engineering, project definition and specifications.
Assistance in operation and commissioning.